Q.1
The Scope Statement should contain which of the following?
A.
Project schedule
B.
Project budget constraints
C.
Summary of project tasks , deliverables and resources require
D.
Project objectives
View Answer
Option: (D)
Q.2
The Scope Management Plan is included in which of the following documents
A.
Project Plan
B.
The Work Breakdown Structure
C.
The Scope Statement
D.
Project Specifications
View Answer
Option: (C)
Q.3
) Project Scope:
A.
s of concern only at the start of the project
B.
is mainly a problem to be handled by the change control procedures during the project execution phase
C.
Should be managed and controlled from the project concept through close-out
D.
Ns usually not a problem after the contract or other document authorizing the project has been approved.
View Answer
Option: (C)
Q.4
The Project charter is created by
A.
The project manager
B.
Upper management
C.
The Vice President over a functional management group
D.
NThe customer
View Answer
Option: (B)
Q.5
The project scope statement furnishes the basis for:
A.
The project scope statement furnishes the basis for:
B.
Provides links to the clients functional management groups
C.
Allowing the project to move to the next phase
D.
A way to provide updated information to the accounting department
View Answer
Option: (A)
Q.6
The Scope Baseline is
A.
the original description of the project’s end results
B.
a summary description of the project’s original content and end product, including basic budgetary and time constraint data
C.
the original project budget and schedule
D.
a and c
View Answer
Option: (B)
Q.7
A Project control system:
A.
Monitors and controls the project’s schedule, costs, scope, budgets etc
B.
Is a mechanism which reacts to the current project status in order to endure accomplishment of project objectives
C.
Is only needed on large mega projects
D.
Is a system for controlling and executing project documentation in an uniform and timely manner
View Answer
Option: (A)
Q.8
)The PM distributed a document to the stakeholders, which described the software to be developed, the functionality, the users it would serve and the installation timeline. The document was an example of:
A.
Product scope
B.
Project scope
C.
A combination of project and product scope
D.
It was not complete enough to be either a product or a project scope document
View Answer
Option: (D)
Q.9
Each item of the Work Breakdown Structure is assigned a unique identifier. What is the name of this identifier?(D
A.
Product ID number
B.
Code of accounts
C.
Quality inspection identifier
D.
Project activity code
View Answer
Option: (B)
Q.10
)When developing a project’s scope statement, which of the following should not be included?
A.
Project justification
B.
Cost/benefit analysis
C.
Project deliverables
D.
Measurable objectives
View Answer
Option: (A)